PPM schedule for commercial plumbing and heating: what to include

By the Field Suite editorial team. Every fact checked against its official source (HSE guidance and the regulations on legislation.gov.uk) on 5 November 2026.

Short answer: a PPM schedule lists every asset on the site, the tasks for each one, how often they are done, who does them and what is recorded. Take each frequency from a named source: the law where it sets one, HSE guidance such as HSG274 for hot and cold water, the manufacturer's instructions, or the client's risk assessment. Then group the tasks into visits you can book.

Why the schedule matters

Several laws require plant to be maintained, but most do not say how often. That is the gap a PPM schedule fills.

  • Workplaces: equipment, devices and systems covered by regulation 5 of the Workplace (Health, Safety and Welfare) Regulations 1992 must be maintained "in an efficient state, in efficient working order and in good repair" and, where appropriate, be "subject to a suitable system of maintenance".
  • Work equipment: the employer must keep work equipment maintained in the same terms and keep any machinery maintenance log up to date (PUWER 1998, reg 5).
  • Gas: every employer or self-employed person must ensure that any gas appliance, installation pipework or flue at a place of work under their control "is maintained in a safe condition so as to prevent risk of injury to any person" (Gas Safety (Installation and Use) Regulations 1998, reg 35).
  • Electrical systems: they must be maintained so as to prevent danger, so far as is reasonably practicable (Electricity at Work Regulations 1989, reg 4(2)).
  • Pressure systems: the user must ensure the system "is properly maintained in good repair, so as to prevent danger" (Pressure Systems Safety Regulations 2000, reg 12), as well as having it examined under a written scheme.

Where each frequency comes from

Sources of PPM frequencies for commercial plumbing and heating
SourceWhat it setsExample
A written scheme of examination (PSSR 2000, regs 8 and 9)The nature and frequency of statutory examinations, set by a competent personProtective devices, pressure vessels and pipework where a defect may give rise to danger
HSE guidance: HSG274 Part 2 (2024), Table 2.1Inspection and monitoring frequencies for hot and cold water systems, adjusted by the risk assessmentCalorifier flow and return temperatures monthly; showers descaled quarterly
The site's Legionella risk assessmentLocal frequencies, where the assessor changes the HSG274 starting pointExpansion vessel flushing anywhere from monthly to six-monthly
Manufacturer's instructionsService intervals and checks for each make and modelBoilers, pumps, booster sets, pressurisation units, water heaters
The contract or the client's standardAnything agreed on top, or a named library of schedulesA client that asks for visits to follow SFG20

Write the source next to every task. When a client asks why the shower heads are done quarterly, the answer is on the schedule.

A note on SFG20

SFG20 describes itself as "the industry standard for building maintenance". It is a paid library of maintenance schedules, and its website says the only way to access the standard is through its Facilities-iQ software. If a client's contract names SFG20, the schedules come from that subscription. We do not reproduce SFG20 content, and Field Suite has no link with it.

Pressure systems

PSSR applies to systems that contain a "relevant fluid": steam at any pressure, or a gas or certain liquids at more than 0.5 bar above atmospheric pressure (reg 2). Hot water only counts as a relevant fluid when it is hot enough to have a vapour pressure more than 0.5 bar above atmospheric, which means well above 100 °C, so an ordinary low temperature hot water heating circuit is not caught by its water alone; the gas cushion in a pressurised vessel can be. HSE's brief guide lists examples including boilers and steam heating systems, compressed air systems, heat exchangers and refrigeration plant. It says a written scheme is required for most pressure systems and "generally speaking, only very small systems are exempted". The main exemption is in Schedule 1, Part II: for systems other than steam, the written scheme and examination duties (regs 8 to 10 and 14) do not apply if, for each pressure vessel, the pressure in bar multiplied by the internal volume in litres is less than 250 bar litres. Whether a vessel on your site is in or out is for the user and the competent person to decide, not the schedule writer. It also says the examination "is not a substitute for regular and routine maintenance". So a pressure system appears twice on the schedule: the examination at the scheme's interval, and the routine maintenance at yours.

What the schedule should list

Columns for a PPM schedule
ColumnWhy it is there
Site and location in the buildingThe engineer finds the plant without a phone call
Asset: type, make, model, serial numberTies the task to the right manual and the right history
TaskWhat is done, in plain words
FrequencyMonthly, quarterly, six-monthly, yearly, or the scheme's interval
Source of the frequencyLaw, HSE guidance, manufacturer, risk assessment or contract
Who does itYour engineer, a specialist, the competent person or site staff
Qualification neededFor example, an employer or self-employed person may only do work on gas fittings if they are a member of a class of persons approved by HSE (Gas Safety (Installation and Use) Regulations 1998, reg 3(3)); HSE points to the Gas Safe Register to check an engineer
Record to leaveReadings, a certificate, a pass or fail, photos
Next dueThe date the visit is booked against
From asset register to records: how a PPM schedule is built Five boxes in a row joined by arrows: asset register, tasks for each asset, frequency with its source, visits grouped by month, and records left on site. A line returns from records to the asset register, because findings change the plan. Asset register Tasks for each asset Frequency and its source Visits grouped by month Records left on site Findings and defects change the register and the plan
The frequency column is the one clients and auditors question most, so each one names its source.

Hot and cold water tasks from HSG274

For hot and cold water systems, Table 2.1 of HSG274 Part 2 gives a checklist with "an indication of the frequency of inspection and monitoring". The risk assessment "should define the frequency" (para 2.79).

Selected tasks and frequencies from HSG274 Part 2 (2024), Table 2.1
AssetTaskFrequency in Table 2.1
CalorifiersCheck flow temperature (as close to 60 °C as practicable without going below 60 °C) and return temperature (not below 50 °C)Monthly
CalorifiersInspect internally and clean by drainingAnnually, or as indicated by the rate of fouling
Hot water services, circulatingTemperatures at return legs of principal loops: at least 50 °C (55 °C in healthcare premises)Monthly
Cold water storage tanksInspect and carry out remedial work where necessaryAnnually
Cold water servicesSentinel taps below 20 °C within two minutes of runningMonthly
Showers and spray tapsDismantle, clean and descale heads, inserts and hosesQuarterly, or as indicated by fouling or other risk factors
Thermostatic mixing valvesInspect, clean, descale and disinfect strainers or filtersAnnually or as the risk assessment defines, taking account of the manufacturer
Expansion vessels on hot and cold water systemsWhere practical, flush through and purge to drainMonthly to six-monthly, as the risk assessment indicates
Infrequently used outletsFlush until the temperature stabilises and purge to drainWeekly, or as the risk assessment indicates

The full Legionella picture is in the HSE documents. For pumps on the same site, see booster set servicing and the pump service checklist.

Worked example: a three-storey office

The plant: two gas boilers, an indirect calorifier, a cold water storage tank feeding a twin-pump booster set, a sealed heating system with a pressurisation unit and its own expansion vessel, eight showers and four thermostatic mixing valves. The booster set and the hot water system each have a potable water expansion vessel. The client's Legionella risk assessment sets flushing of those potable vessels at six-monthly; HSG274 Part 2 covers hot and cold water systems, so its flushing task is for these potable vessels, not the closed heating circuit. The client asks you to take on the monthly temperature checks. The weekly flushing of little-used outlets stays with site staff, as the risk assessment says.

The office's visit plan for one year
VisitMonthsTasksSource
Monthly water visitEvery monthCalorifier flow and return, hot water return legs, cold water sentinel tapsHSG274 Table 2.1
Quarterly visitMarch, June, September, DecemberThe monthly tasks, plus showers descaled, booster set and heating pumps checked for leaks and test-runHSG274 Table 2.1; contract
Six-monthly visitJune, DecemberThe quarterly tasks, plus the potable water expansion vessels flushed and purgedRisk assessment
Annual visitJuneEverything above, plus calorifier inspection, cold water tank inspection, TMV service, boiler service, booster set vessel precharge and pressure settingsHSG274 Table 2.1; manufacturers' instructions
PSSR examinationAs the written scheme saysOnly for parts the competent person includes in the schemePSSR regs 8 and 9

That is 12 visits a year, with the heavy one in June, when the heating is off. Booking the boiler service then is a planning choice, not a rule. If the risk assessment changes, change the plan and note why. To cost the plan, see pricing a PPM contract. To start from a ready-made sheet, use the PPM schedule template.

Who does what

PPM duties by role
WhoWhat they do
The client (employer, or whoever controls the premises)Holds the maintenance duties above, owns the Legionella risk assessment and agrees the schedule
The PSSR userMakes sure there is a written scheme and that examinations happen at its intervals (regs 8 and 9)
The competent person under PSSRDraws up or certifies the scheme, examines the system and sends a signed, dated written report
Your firmBuilds the schedule, carries out the tasks, records results and reports defects with how urgent they are
Site staffTasks the risk assessment gives them, such as weekly flushing of little-used outlets

What to record

  • Each task done, the date, and who did it, with their signature or another form of authentication (L8, paras 73 and 74)
  • Readings as found, such as temperatures and pressures, and results of any check or test
  • Remedial work needed and done, with the completion date (L8, para 74)
  • A log of contractor visits (L8, para 74)
  • Defects found, with urgency and a recommendation
  • For pressure systems, the competent person's last report, kept at the premises or approved premises (PSSR reg 14)

HSE's L8 says to keep Legionella monitoring, inspection, test and check records, with their dates, "for at least five years" (para 72).

Running a PPM schedule in Field Suite

  • Equipment register: each asset at its site with make, model, serial number, service interval and next due date.
  • Contracts: visit lines that repeat every set number of months, each with a form to fill in. Field Suite creates the job a set number of days before it is due (21 by default), and moves the due date on. Visits are set in whole months, so weekly tasks stay with site staff or a separate arrangement.
  • Forms on the phone: ready-made forms include a pump service checklist. The ready-made gas safety record is the landlord's record for let homes, so for water temperatures or a commercial boiler service, add your own questions in the form builder.
  • Import: bring an existing schedule in from a spreadsheet, one row per visit line. The template has the right columns.
  • Faults: engineers record what they find with how urgent it is, and the office turns the faults into a quote.

See planned maintenance software, pump maintenance software and subcontractor management for specialist visits, read about sewage pumping station maintenance and what a job sheet should show, check prices, or book a demo.

Field Suite is job management software. The law, the manufacturer's instructions and the site's own risk assessments decide what is maintained and how often.

Questions

Is there a legal PPM frequency for commercial boilers?

The Gas Safety (Installation and Use) Regulations 1998, reg 35, require gas appliances at a place of work to be maintained in a safe condition, without setting an interval. Use the manufacturer's instructions and record the source.

What is the difference between a PSSR examination and a service?

The examination is a statutory check by a competent person under a written scheme. HSE says it "is not a substitute for regular and routine maintenance", so both go on the schedule.

Can the Legionella risk assessment change HSG274 frequencies?

Yes. HSG274 says the risk assessment should define the frequency of inspection and monitoring, and several rows in Table 2.1 say "or as indicated by the risk assessment".

Do I need SFG20 to write a PPM schedule?

No law requires it. Some clients name it in their contracts, and then the schedules come from an SFG20 subscription.

Sources

Last checked: 5 November 2026 against the sources above.

Checked in detail: HSE HSG274 Part 2, L8, INDG261 and Gas Safe Register page, PSSR 2000, Workplace Regulations 1992, PUWER 1998, Gas Safety Regulations 1998 and Electricity at Work Regulations 1989 on legislation.gov.uk.

Field Suite is job management software for UK building services firms, not a consultancy. Your own risk assessments, contracts and advisers decide what applies to your work. Spotted a mistake? Email info@fieldsuiteapp.com and we correct it.

Run the work and the records in one place

14 days free with every feature and up to 10 users. No card details and no contract.